SEYMOUR-CAPILANO TWIN TUNNELS COMPLETION PROJECT

In 2009, Frontier-Kemper ULC, J.F. Shea, and Aecon (Seymour-Cap Partnership) took over the contract for twin, 12.5-ft. (3.8m) diameter, water tunnels for the Greater Vancouver Water District. When completed, one tunnel will be used to transport raw water from the Capilano Reservoir to the Seymour Treatment Plant, and the second tunnel will return the treated water to the Capilano Water Distribution Network. In addition to the TBM tunnel excavation, work also includes:

  • Tunnel Support & Control of Groundwater
  • Drill & Blast Excavation of Underground Chambers
  • Excavation of Twin, 4m diameter, 270m deep, Raise Bored Shafts
  • Installation and Backfill Grouting of Steel Lining in all Shafts and portions of the tunnels
  • Interconnection Pipes from the Shafts to nearby water mains

Services/Methods Performed:

FAST FACTS:

LOCATION: North Vancouver, BC

MARKET: Water/Wastewater

OWNER: Greater Vancouver Water District

CONTRACTOR: Seymour-Cap Partnership (FKC ULC / J.F.Shea / Aecon JV)

START DATE: April 2009

END DATE: March 2015